Category Archives: U-District Light Rail Station

The First TBM Arrives!

November 6, 2015

The first of two tunnel boring machines (TBM) arrives after tunneling from the Roosevelt Station site. The construction crew nicknamed this machine “Brenda” for reasons that aren’t entirely clear. You can get more information from the official web siteĀ http://www.soundtransit.org/northgatelink.

7 – Site Excavation Continues

October and November 2014

The digging and site preparation continue into the fall of 2014.

6 – Site Excavation Begins

September 2014

Excavation of the light rail station box pit started slowly as the foundations of the demolished buildings had to be removed.

5 – Boring the Excavation Support Pilings

April through July 2014

The station box excavation uses two different retaining wall configurations. The east and west walls used steel H-beam caissons lowered into bored holes. The pit was excavated to a depth of 90 feet. The caissons are 120 feet long with holes bored that deep. The bottom 30 feet are filled with concrete to provide a foundation for the caissons. The space between the caissons was filled with wooden timbers known as lagging. The north and south walls used bored holes filled with rebar and/or steel H beams and concrete. The areas where the light rail tunnels will be located used fiberglass rebar as reinforcing.

4 – UW Tower Chiller Lift

April 21, 2014

A chiller is one of the major components of a large building’s HVAC system. The UW Tower, a 22 story building constructed in 1974, needed to have its old chiller machinery replaced. The chiller is on the roof. It requires a rather ginormous crane to lift heavy machinery to the roof of a 22 story building. The best time to do this was when the adjacent lot had been cleared to make way for the light rail station.

Some of the above photos, those labeled “SoundTransit_20140421xxxxx”, were taken by the Sound Transit web cam atop the Neptune theater.

3 – Site Preparation

January and February 2014

After the building demolition the site was graded and covered in asphalt. A large vertical boring machine was assembled to start drilling the holes for the caissons and pilings that would provide support for the walls of the excavation.

2 – Demolishing the Existing Buildings

May through June 2013

The buildings on the site were removed to make way for the light rail station.